I now have an update and Pilgrims Way will be reopened, most likely late tomorrow (Wednesday) evening. In any case, it will be open before 0600 Thursday.
There are currently three sets of excavations by SGN and these will be filled in and left to cure in the course of tomorrow. The reinstatement needs to cure (harden); if traffic goes through the road before this, there could be damage to the road and the need for a yet further closure.
While these works have been going on, KCC has used the closure to carry out three sets of works in Pilgrims Way, addressing kerbing, drain cleansing and potholes at the edge of the carriageway. As a result, the closures that I highlighted originally for the end of this week are now thankfully not needed.