Wested Lane closure delayed

Residents of Crockenhill and neighbouring areas have experienced severe disruption on a number of occasions reflecting ongoing Network Rail works, which in particular have closed Wested Lane.

A further, quite lengthy closure was due to start this morning (running for eight days, 14-21 September). KCC Streetworks raised challenges over the length and impact of the closure, but Network Rail and their contractors were clear that the complexity of the works, and the inability to store equipment on site overnight, meant that the length of the closure could not be reduced. 

However, the closure has now been delayed because Network Rail wanted to prevent disruption to train services to London in the days leading up to and including that of Her Majesty Queen Elizabeth II’s state funeral. At present we do not have a new date for the closure.