The road closure in School Lane in Seal planned to start tomorrow (5 August) has been delayed for a fortnight. The ten day road closure will now start on 19 August.
The closure (outside 1-3 The Green) is for Thames Water to deal with a collapsed sewer some three and a half metres under the road surface and to install an inspection cover in the road. Given the lengthy detour required by the alternative route (A25/ A225/ Pilgrims Way East/ Childsbridge Lane) KCC Streetworks requested extended working hours and weekends to complete the works as quickly as possible. I understand that the delay to the works is because resources were not available to deliver on these extended hours at this time.