Roger Gough

Sunday 10 May 2020

Footway surface improvements in Sounds Lodge

Surface improvement works on the footways in Sounds Lodge, Crockenhill, will be carried out in the coming weeks. The surfaces, which have been showing signs of wear and deterioration, will be treated by 'slurry sealing'.

The works will be undertaken in two phases. The first stage, starting on 20 May and lasting for three days, will affect nearby grass verges and also power washing of the footway surface. In the second stage, lasting three days from 15 June, a new surface treatment will be applied. In both cases the works will take place between 8 am and 5 pm.  The paths should be able to be opened up within an hour or so of the new surface being applied.

No comments:

Post a Comment