Wednesday, 19 March 2025

Tackling drainage in Watery Lane


Watery Lane will be closed overnight from tomorrow night (20 March) for up to two nights. The closure will be between 8PM and 5AM, and the closure will be from Chaucer Business Park to the junction of Saxbys Road. This is for KCC to undertake drainage works to address the long-standing problems on the road. 

While there are a number of factors affecting Watery Lane, in particular the interaction between the Network Rail drainage system under the bridge and the Kent Highways drainage system, the works to be undertaken over the next couple of days will focus on the latter. There will be a thorough cleanse of all the gullies, catchpits and manholes and jet all the pipework in the Kent Highways system in that section of the road.

Once these works have been completed, and it is confirmed that they have been effective (our drainage engineer will review the works on completion) the Highways Operations team will be able to carry out the necessary repairs to the road surface; they have been unable to do so as long as the water is running.

Hopefully these works will provide some relief from the problems that have affected this section of road. I will post again when there are further updates on how the works have gone and when the road surface repairs can take place.

Monday, 17 March 2025

Pilgrims Way closures

A quick note on today’s significant disruption on Pilgrims Way and Pilgrims Way East. 

The Pilgrims Way closure (between junctions with The Landway and Old Terrys Lodge Road) was for urgent highway works by KCC - patching that needed to be undertaken rapidly. These works are set to go on through to the end of the week.

When these works were under way, BT Openreach closed PWE between Tudor Drive and Row Dow under emergency closure provisions (I’ll come back to the merits or otherwise of that shortly). As is usual in these cases, KCC was not notified until after the road was closed.

My thanks to Simon Reay for highlighting that there were severe problems/ deficiencies with the signage and access for residents on the KCC Pilgrims Way works. I took this up with the Streetworks team and got the following information/ action.

The surface for the patching work in Pilgrims Way will reinstated tomorrow and Wednesday, and from Wednesday the section between The Landway and Cotmans Ash Lane should be reopened. Between Cotmans Ash Lane and Old Terrys Lodge Road will remain closed until Friday. Residents should already have access to their homes, although there may be delays while specific sections of the road are made safe for that access. The Streetworks Inspector will attend the site tomorrow morning to make sure the right signage is in place.

This should not have been as disruptive as it was, and I am sorry for the bad experiences residents had today; hopefully these steps will make the situation a lot more manageable for the remainder of the works. 

In relation to PWE and the BT works, Openreach confirmed at 1:15 that they were complete and the road was being reopened. What this does highlight, though, is the use made of emergency provisions. KCC (and other highway authorities) has been raising this issue for some time. A change in national policy is required. Fortunately, the House of Commons Transport Select Committee is carrying out an inquiry into the issue because it is a major problem across the country. KCC put in a very strong submission to the Inquiry and so we have been invited to give evidence this week.

Finally, all this is separate from the highways improvement works on Pilgrims Way East next week (24-25 March), which as anyone who has driven through there will know, has been notified for some time.

Wednesday, 19 February 2025

Park Lane works completed

The works and road closure in Park Lane Seal have been completed well ahead of schedule. 

The contractor had completed the works by late on Monday (the first day) and so the road was already open throughout yesterday - which is why there seemed to be no evidence of the closure by late afternoon. 

The original closure was scheduled for up to five days. Given the difficulty of alternative routes when Park Lane is closed, it is good that the contractor was able to allocate extra resource to the works and so minimise the disruption to residents and to the wider road network.

Friday, 14 February 2025

Park Lane Seal closure from Monday

The emergency closure of Park Lane Seal next week was announced yesterday. The closure, between the junctions with Blackhall Lane and Bichet Green Road, will start on Monday for up to five days (17-21 February). This is for essential safety works to trees on unregistered land that Kent Highways is undertaking under its statutory duty of care. Because of the width of the carriageway and the height of the trees the road has to be closed in full rather than a single lane.

The closure is permitted between 8am and 5pm for each day but may on occasion be shorter. The road will reopen when the contractors leave the site each evening. In addition, while the work is scheduled for five days, it is hoped to be less; significant contingency for bad weather, break downs and other delays is built in. 

Any closure on a road like Park Lane will be disruptive, but hopefully scheduling this in half term and delivering the works promptly will minimise this.

Thursday, 30 January 2025

Potholes in Old Chapel Road

Many thanks to Rachel Waterton for raising the issue of the potholes on Old Chapel Road, scene of yesterday’s accident. I have taken this up with Kent Highways officers. A job was raised yesterday morning for a 7 day repair, but in addition one of the highways officers will revisit today to make sure they are safe in the interim.

Wednesday, 8 January 2025

Franks Lane bridge vandalised again


For a second time, repairs to the bridge in Franks Lane have been subject to vandalism. Following the severe damage done before Christmas, this week’s works were found to be vandalised last night (thanks again to Cllr Alan White for this picture). 

There is a significant history of vandalism on this site, but this is especially sickening. I have spoken to the KCC Structures team who have been working on this, and KCC, SDC, Police and other relevant bodies will need to come together to find a lasting resolution to this.

Sunday, 5 January 2025

Franks Lane repairs

Kent Highways have notified an urgent road closure on Franks Lane, starting tomorrow for 2 days. The road will be closed at the bridge between 9:30 AM and 3 PM each day. 

This is to enable the brick parapet, damaged by vandalism shortly before Christmas, to be rebuilt and matches the timetable I was told at the time. At present, I have not heard that the works will be affected by the current severe weather, but will of course post again if that changes.

Sunday, 22 December 2024

Franks Lane bridge works vandalised

Many Horton Kirby residents will have seen that the works on the Franks Lane bridge, running through the week commencing 16 December, have been vandalised. This took place on Thursday, and as the picture shows (photo credit: Councillor Alan White) the new brick work has been pushed into the river.

This is the most dismal and appalling vandalism, and comes when the works were heading to completion. I have been in contact with Kent Highways officers, and contractors were due to attend and assess the damage on Friday. I was told that they plan to return during the week beginning 6 January, provided that the materials needed for the works are available. I will update when I know more.



Thursday, 12 December 2024

Franks Lane: closure for bridge repairs next week

Repairs will take place to the Franks Lane bridge in Horton Kirby at the start of next week. 

KCC officers attended the bridge on 29 November to inspect the damage (a large part of the parapet wall knocked into the river, more damage to the remaining part) and make plans for repair. 

The road will be closed (9:30 to 3:30) for up to five days starting Monday 16 December. Officers are hoping to maintain pedestrian access when it is safe to do so during this period. While repairs are carried out, new signage warning of narrow bridge ahead will be installed directly on to the brickwork of the parapet.

Tuesday, 29 October 2024

Vital safety works to start on the A20

As many residents have seen from the Start of Works Notice (SOWN) issued a couple of weeks ago, KCC/ Kent Highways will be carrying out significant works to enhance safety on the A20 near Farningham, starting on 4 November.

 The central feature of the works is to install a system of average speed cameras in the area of the 40mph zone to the east (West Kingsdown facing side) of Kings roundabout. This follows extensive work and analysis of the factors behind the serious and fatal accidents that have taken place on this stretch of road. Driver error (often not on the part of those who were the victims of the crashes) was a common feature, but speed made the effects much more severe. This is the logic of the average speed camera installation, and is in accordance with the thinking behind KCC’s Vision Zero Strategy – that you can never fully eliminate driver error, but you can take measures to reduce and mitigate its effects.

In addition, KCC will be installing 40 mph roundels on that stretch of road, countdown markers on the approach to the 40mph gateway, just north of Charton Manor, and will enhance the current high friction surfacing at the A20 main Road junction with the A225 Eynsford Road with a higher skid resistant asphalt surface. The countdown markers, which originated in discussions that I held between Kent Highways and the Parish Council, are an unusual step, and required some discussion with the Department for Transport.

I have been asked why these measures have not been applied on the Swanley-facing side of the roundabout where there is a lot of concern about speeds as vehicles head towards Swanley. However, this would not be possible under the criteria for cameras of the Kent & Medway Safety Camera Partnership (which themselves reflect national guidance). We are, however, looking to signage options that will help to address this.

In recognition of continuing concern over illegal right turns at the Eynsford Road/ A20 junction, Kent Highways will also be enhancing the signs and lines at the Eynsford Road junction to emphasise the existing No Right Turn restriction in place. It is important that these measures are demonstrated to have been tried before any other measures to enforce the restriction are attempted; but the situation will be monitored and if justified those further measures could be introduced.

The work will take around two weeks to complete, commencing on 4 November 2024 (next Monday), with the signing and vegetation cut back taking place between the hours of 09:30 and 15:00.

Installation of the average speed cameras will take around four days to complete, commencing on 5 November 2024, between the hours of 20:00 and 05:00.

Lining and high friction surfacing replacement will take place between the hours of 20:00 and 05:00 during the week commencing 11 November.

All this is subject to potential change depending on weather conditions, and the works will be carried out under multi-way traffic lights.

This should represent an important step forward in terms of road safety in an area with a long and tragic record of accidents; and many of the other issues in the area will remain under Kent Highways’ attention, and mine as the local Member. The work does not stop here. 

Friday, 26 July 2024

Road improvements on the A20

There will be two closures on the A20 in the next couple of weeks to allow for highway improvements.

Next Tuesday (30 July) the road will be closed between 0430 and 0700 for surface dressing works. The closure will be between the junction with the A225 Dartford Road and the speed de-restriction signs outside Charton Manor Farm.

There will then be a 20mph speed limit in that part of the road until the concluding works (on Monday 5 August) to seal the surface dressing. This will use a technique called lockchip - which pretty much does what it says, with a bitumen coating binding in the chippings and reducing loose material on the road. 

The closure on the 5th will be for a relatively short period of time- approximately an hour - at some point between 0930 and 1530. It will, however, require a complete closure of that part of the road for that time. 

There will be similar works (surface dressing on the 30th, sealing on the 5th) elsewhere on the A20, at London Road Wrotham, but the timing will be different from those near Farningham. 

All these works are, of course, subject to weather but hopefully can be carried out in a way that minimises inconvenience to drivers and delivers road surface improvements.

Thursday, 13 June 2024

Defects on PWE speed ramp

I’ve taken up reports of vehicles being damaged and a defect on the speed ramp near the Row Dow junction in Pilgrims Way East with Kent Highways. They have sent someone from the contractor to investigate it this afternoon/ evening. I’ll post any further information when I get it.

UPDATE: A further update on PWE … The contractors have attended and located two curbs that are coming loose and will need resetting. They have been made safe for now pending a more lasting fix. 


Friday, 7 June 2024

Completing 20mph in Swanley Village

Following up on the incomplete installation of the 20mph area in the village last week - contractors will be returning to install the unfinished roundels on 27 June. Apparently there was a medical emergency on site, which was the reason for their not being completed as scheduled.

I have also asked about the sign that was left in the hedge row opposite Jasmine Cottage. This has been taken up with the contractors and they are being asked to come back and collect it – hopefully early next week and certainly well in advance of their return on 27 June. 

Tuesday, 16 April 2024

Unacceptable closure in Sevenoaks

Many residents will have been badly affected by today’s closure of St John’s Hill in Sevenoaks.

South East Water have been carrying out works on the road on a permit from Kent Highways for an overnight (2000 – 0500) closure for three nights starting last night. The terms of the permit were that the road would be open during the day, without any traffic management measures. However, this morning the condition of the road was affected by the works and the road closure was left in place (without the local Streetworks team being informed). It is this that has caused today’s severe traffic problems.

This is completely unacceptable; the matter is being escalated by our officers and I will separately be writing and taking the matter up with South East Water. Work is now underway with the aim of being able to open the road for tomorrow morning, although at present I cannot confirm whether this will happen.

Wednesday, 10 April 2024

Streetworks and road closures

Severe traffic problems after an accident on the M25 - but coming at a time of a lot of road closures, in particular for planned SGN works on the A25 at Sundridge - sparked a lot of debate on local Facebook pages. Given this, a few comments from me on Streetworks and their implications are in order. 

The general position on Streetworks is that the utilities are ‘statutory undertakers’ - they have a right to use the highway when needed for their works and there is little scope to refuse them. Planned works are discussed with KCC/ Kent Highways and they make a major effort to coordinate them … BUT the sheer volume of works (up sharply in recent years across the country), along with efforts to limit disruption in relation to (for example) school travel makes this challenging … AND this is often made much worse by emergency works, which can play havoc with planning. In that case, the utility acts first and informs the highway authority within two hours of starting. About a third of works in Kent are emergencies, and to the best of my knowledge this is similar elsewhere; I hear the same concerns from my counterparts in other counties.

Emergencies explain a lot of the situations when wider areas experience severe disruption, though this wasn’t the case in the incident that sparked the debatereflecting instead a horrible crash on the M25. 

The problem for local authorities, including Kent, is that our legal position and powers are relatively weak. We have, along with other councils, argued for change and we continue to review what we can do within the existing setup; we will be reporting back on that work in the coming months. We are only too aware of how disruptive this is.

Thursday, 7 March 2024

Road closures in Swanley Village

 Some updates on road closures in the village. 

Tomorrow (Friday 8 March) there will be the long-delayed closure of Gildenhill Road for Kent Highways to carry out carriageway repairs. The closure will be between 9:30 and 2:30 and will be between Church Road and Clement Street.

There are still some works due to be carried out on Highlands Hill too but they have again been put back because of other works going on. 

A little further out, Highlands Hill will be closed (10-11 April) for Thames Water works on a fire hydrant. This will be a full road closure (apparently the works will be in the middle of the road) and will be continuous (in other words, including overnight). It is, however, during the half term period and is scheduled for that purpose to avoid disruption to the school. 

There will be a separate closure by KCC on Highlands Hill (to replace a street lighting column) on 30 April, but that will only be between 9:30 and 2:30so once more, this will avoid having an impact on school drop-off and pick up. 

More immediately, the works at the bottom of Highlands Hill (a company called Triconnex providing electricity and gas connections to the development on the old nursery site) are going from two way to four way lights as the works have reached the junction with Swanley Lane. (This took place either yesterday or today). The four way lights, which are manually controlled from 7am to 7pm to ease congestion, will be on for a relatively short time as they become two-way again as they move up the road towards Hextable. All the works should be completed by 22 March. 

Thursday, 15 February 2024

Pilgrims Way reopened

Pilgrims Way is now open, and the South East Water works are complete. 

The Traffic Management signs are still up, but the company which supplies them will be retrieving them shortly. Our Streetworks team has sought to get the utility to get these works completed ahead of the scheduled three days, and they are now done.

Wednesday, 7 February 2024

Swanley Village highways works next week

Kent Highways works on potholes on Highlands Hill and on Gildenhall Road, scheduled for last week, were delayed following sickness among the gang who were due to carry them out. They have now been rescheduled for next Monday, 12 February, and so by taking place in half term should avoid causing difficulties for school drop off and pick up.   

The potential problem is that this is also bin collection day. However, SDC have been informed of the closure (they are on the Streetworks mailing list for closures) and the two councils have been in contact. The collections will take place quite early on Monday (please note!), any time from 7 am but certainly out of the area by 9:30, which is when the highways works get under way. Road closures in each of the two roads should not last more than two hours per road, though the formal closure allowed for on Highlands Hill (which will affect the whole road) is between 9:30 and 2:30.

Sunday, 4 February 2024

Counting down to EES

In the course of the last week, I had the opportunity to highlight to a parliamentary committee the challenges to Kent from the anticipated introduction of the European Union’s Entry Exit System (EES). You can find Kent County Council’s media release on this here.


Deirdre Wells, chief executive of Visit Kent, Andrew Osborne, head of economic development at Ashford Borough Council and I gave evidence to the House of Commons European Scrutiny Committee on Wednesday. EES, which brings with it requirements for biometric checks on entry to the EU external frontier, is now expected (after a number of delays) to be introduced in October. This raises the prospect of long delays because of the very constrained space within the Port of Dover, resulting in further large scale disruption to Kent’s roads, businesses and visitor economy, in addition to its impact on the quality of residents’ lives.

We had a good hearing from the Committee, and I set out the need to ensure that, at the very minimum, there is extensive communication and preparation; but we must make every effort to present the case for some form of pre-registration. While Kent County Council and our partners in the county will more than play our part, this is above all a matter for government. We are seeing government respond to this approaching crisis, and raised this successfully in a recent visit by the Roads Minister, Guy Opperman. But as I pointed out, we are not yet seeing the scale of government focus and preparation that we had in the run up to the end of Brexit transition in 2020. Yet the effects could be at least as great.

Wednesday, 31 January 2024

Pilgrims Way East: works at the weekend

Many residents will have seen from the signage up in Pilgrims Way East that there will be a further closure this weekend. The closure will be between the Tudor Drive junction and the A225 Shoreham Road, and will be from 7:30 am on Saturday 3 February until 11:59 pm on Sunday evening. 

The works are to address the deficiencies on the tabletop by the Tudor Drive junction, and the outcome should be something more like the tabletop at the Row Dow junction. This design also requires less time for the curing of the kerbs. 

The recommended diversion route is, as before, via Childsbridge Lane, the A25 and the A225 Sevenoaks Road and Station Road.