Pages

Thursday, 22 July 2021

Road closures affecting Seal, Kemsing and Otford

With the school summer holidays getting under way, there are a number of major road closures taking place that affect Seal, Kemsing and Otford, the more so since there is an unavoidable overlap. 

In Otford, there will be a rolling programme of works to deliver significant parts of the village highway improvements and associated closures starting from next Monday. These are (with associated permit numbers):


    26th July – 2rd August,  multi way lights Station Road, Shoreham Road & Pilgrims Way East.  Permit reference GE40190203817, for road markings, tactiles paving for crossing & kerbing works.

    2rd – 8th August, two way lights Station Road near to Beckets Place.  Permit  reference GE40190203818,  for  removal of road markings and verge installation.

     9th -  20th August, High Street, Otford closed between No.s  48 12.  Permit reference GE40190203820, for construction of new raised zebra crossing.

     9th – 20th August, High Street, Otford between No.s 53 – 69, 2 way traffic lights. Permit reference GE40190203819, for road markings, sign installation, build outs for traffic calming.

   20th -28th August works around Otford Pond, Station Road, Sevenoaks Road & High Street, multi way lights / stop and go (not at the same time). Permit reference GE40190203823, for road markings, bollard and planter installation, crossing upgrade, vegetation.


Meanwhile, UKPN works to install a low voltage cable will start in School Lane, Seal. This will require traffic lights from 26 July to 1 August, and the road will then be closed between the A25 and Childsbridge Lane starting from Monday 2 August for 18 days (ie until 20 August). Works will also be carried out by South East Water during the first week of the closure.

The full closure will have the effect of preventing vehicles going north off the A25 through Seal towards Kemsing. The recommended diversion route is west along the A25, north on the A225 and then through Pilgrims Way East and Pilgrims Way to Childsbridge Lane. The southbound route on Childsbridge Lane to the A25 is unaffected by these scheduled works. 

The coincidence of these works over a period of up to 18 days, and the impact of traffic diverting through the A225 and Pilgrims Way East have been a cause for concern and I have taken these issues up with Kent Highways. However, the works in question are either the delivery of a long developed scheme aimed to deliver benefits to Otford and its residents, or clearly essential works for UKPN to carry out. And both would cause much greater havoc in term time. 

Kent Highways considered alternative diversion routes, and are certainly very aware of the problems of diverting traffic through parts of Otford affected by the works, but concluded that this was nonetheless the least damaging option. However, a recommended diversion route is just that: there is nothing to stop those with local knowledge choosing another route. 

To reduce disruption and improve traffic flow, the traffic lights on School Lane (week of 26 July - 1 August) will be manually controlled at peak times (0730 to 0930 and 1530 to 1900). Similarly, the lights at the Shoreham Road/ Pilgrims Way East junction will only operate when staff are on site, and they will be manually controlled if needed. 

It is also worth noting that there will be some overlap with yet further works, albeit night time works only, on the A225 Shoreham Road for 14 nights starting 27 July. This is for road resurfacing and will require closures (2200 to 0600) from Castle Road Lullingstone to Station Approach in Otford. This will require a major diversion by any traffic using the route at that time but will not, however, affect traffic during the day.

No comments:

Post a Comment